Reporting Configuration Based On User Story Points

The current configuration in JIRA Reports for  Burndown charts is on the basis of total time/effort spent OR time remaining on the user story. 

How can we configure JIRA to generate reports on the basis of user story points consumed ? 

e.g if i have a story of 10 user points and on the 3rd day I have finished work equivqlent to 3 story points, I  should be able to mark progress on the user story as 3 points completed and the burn-down-chart should be generated accordingly. 

1 answer

There should be a configuration in your Agile Board to change this: 

  • Open your SCRUM board and click on "Board >> Configure"
  • Click on the "Estimation" tab 
  • Change Time Tracking to your need
  • Change the value of the "Estimation Statistic" (If needed)

 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

775 views 3 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you