I have time tracking enabled on my project. We have entered the estimate are are tracking work. However I would expect that the remaining time would show the estimated time lesds the total of the logged work. It is not. It is showing the total logged work instead. I'm figuring this is just a setting I have that is incorrect, but I having been test it and I can't seem to get it to change. Can someone assist me?
Yes, I think it does. Thank you. I did edit and it is displaying now as anticipated. We will see if it now updates as expected once we log more hours. TX
You are welcome, Danielle!
Have an awesome new year and let us know if you find any other questions regarding this matter.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Danielle,
Can you please provide us a screenshot of the view you are referring to? Are you using the new issue view or the old issue view?
Normally, the time Tracking is displayed in three fields of the issue view or in a single one displaying the logged time against the remaining.
Old issue view:
New issue View:
Can you please let me know if you do not seem this field like this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We are using the Old Issue View and that is a great example of what I am seeing. I would expect to see that remaining would be = to the Estimated - the logged. See attached
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Danielle,
The behavior you are expecting is the default when you don't set any value for the remaining field, just like displayed in the screenshot provided in my last answer.
That being said, the remaining field should be Estimated - Logged if you leave it blank instead of manually add a different value to it.
To correct the fields that are not displaying as you expected, you will need to manually edit the remaining to the correct estimated value.
Please, let me know if it makes sense to you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
I'm experiencing something similar. I have a Task with the Original estimate of 160 hours. We have a team that creates sub-tasks and have logged hours under each sub-task. How can I summarize the logged hours of the sub-task AND deducted from the Original so that it shows in the Remaining? See my screenshot
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can sb help here?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Same issue here. When a subtask is added WITHOUT and estimate, and then Time is tracked against it, only 'Logged' in the parent Story is impacted, not the 'Remaining'.
Is there a fix or a workaround?
also...we don't want to impact the Original Estimate on the Story.