I am looking at the Release Burndown Chart for a Version. There are more than 4 completed Sprints, however the Release Burndown chart does not show the forecasts. I am seeing the following message.
A forecast cannot be shown until at least 3 sprints have been completed"
Please help. Is there any configurations that I need to do to include the completed Sprints, so that I could see the Forecast.
Hi Sheik,
On the Release Burndown Chart page, do you see "Completed Issues"?
Hi Michael,
Yes I see Completed Issues. My question is, I have completed issues in the Past Sprints as well (OB SP 7,OB SP 8, OB SP 9, OB SP10) But the Release Burndown chart shows Sprint bar only from OB SP 10 and OB SP 11 and I am not able to see the forecasts because Jira says "A forecast cannot be shown until atleast 3 sprints have been completed"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.