Добрый день! Подскажите, почему при создании нового спринта закрытые задачи в предыдущем все равно переходят в новый спринт?
Hello, Good day. Following scenario will move an done/completed issue to next sprint.
1. Done status is not mapped to the last column on board settings >> column mapping. Make sure done status is mapped to the last column. https://confluence.atlassian.com/jirakb/closed-or-resolved-issues-get-automatically-added-to-a-new-sprint-1283493370.html
2. Done issues do not have a resolution. Status is moved to done status, but there is no resolution on issue. https://confluence.atlassian.com/jirakb/how-to-edit-the-resolution-of-a-jira-issue-313467778.html#:~:text=Now%20click%20on%20the%20Post,'Fixed'%20or%20any%20resolution.