Problems with Timesheet report and subtasks

Chris Blackstone February 3, 2014

When I run the Timesheet Report for a Particular project, I get 2 very different numbers for "Total Hours" depending on whether I have the "Sum Subtasks" checkbox checked or not.

However, this project has NO Subtasks, so checking the checkbox shouldn't make a difference.

Why is the total Hours calculation changing?

2 answers

1 accepted

1 vote
Answer accepted
Henning Tietgens
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 4, 2014

Maybe you have Epic-Story Links? These are considered like subtasks, too.

0 votes
Chris Blackstone February 4, 2014

Thanks, that would explain it.