Original Estimate value in jira does not match the export in CSV

Sebastian Somi May 5, 2023

Any Ideas why this can be happening?

 

image.png

image.png

Something seems to be off as I am not getting 1w3d

image.png

1 answer

1 vote
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 5, 2023

I think your arithmetic doesn't match the time tracking settings.

310,500 seconds is 86.25 hours, so that bit looks right, but an 8 hour working day turns that into 10.7 days and a 5 day working week makes it 2.2 weeks.  I suspect you don't have Jira set to a 5 day working week, as 1w 3d would be 10 days for a 7 day working week.

Sebastian Somi May 8, 2023

Hi @Nic Brough -Adaptavist- thanks for your response:

Here are our settings (We actually use 7,5 h days):
image.png

image.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events