I have 4 total projects. I created a new workflow. I can seed the new project applied in settings, but my Board still shows the original default workflow. How do i update my projects & their boards with the new workflow i created? Thanks!
Hi Melissa, welcome to the community. What you need to do is go into project settings > workflow and associate the new workflow. If you are simply editing the current active workflow then you should just need to publish after editing. Now, depending on the changes you may need to go into the board settings to map any new statuses into columns.
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.