I have multiple columns which are considered as Done status. But on sprint complete it accepts only the Uat Done as complete rest of the status it considers as Open item and asks to mark them Uat Done or move them to next sprint.
Hi Ravalman,
Only the far right column (last column) is considered to be done for Sprints, regardless of the status name or category. For Company-managed projects, that last column can have multiple statuses in it.
Hi @ravalman,
As mentioned already, in Jira, only the last board column is considered as done. So one solution would be to map all the done statuses on that column, in the agile board's configuration. Obviously, this solution is not ideal, because it forces you to have a single "done"-category column on your board.
But, if you consider a plugin as a potential solution, by aware that our Great Gadgets app offers gadgets like Sprint Burndown Burnup Chart gadget, Release Burndown Burnup Chart and Team Velocity that support multiple done statuses. They will allow you to properly track the project, in the way you want.
You have 1 month of free trial and it is free for up-to 10 users.
Hope this helps. If you have any questions, you can contact support@stonikbyte.com.
Thank you,