Managing Stories that are QA done but not deployed on Prod

Raghav Rajagopal March 24, 2023

Hello Team,

I have a project wherein the stories are Developed and Tested within the sprint but are deployed on Prod at least a week or two after due to PO Approval UAT Testing and Production deployment process, etc. Sometimes Prod deployment happens with features developed in 2-3 sprints ( as part of a single Release)

We have another Kanban board where we track the statuses after QA.

So it goes like this:

Board 1: To Do --> In Progress --> QA --> Ready for PM Acceptance

Board 2: Ready for PM Acceptance - UAT - Prod - Done

As for our team, we have completed the work picked up in the sprint so it is 'Done' for the Sprint. However, when we close the Sprint after testing, the stories/issues are not considered as completed by the Sprint Reports. Jira still considers them as Spill overs and it impacts the velocity.

How do we handle such scenarios? Any suggestions / advice is truly appreciated. Thanks in advance!

 

1 answer

0 votes
Pasam Venkateshwarrao
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 24, 2023

Hi @Raghav Rajagopal 

 

As my understanding you need to set the sprint goal and the start and end date then it will show like this.i Hope this will helpScreenshot 2023-03-24 at 4.58.37 PM.png

Suggest an answer

Log in or Sign up to answer