The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Log Work should only ask for estimation and not for the time spent within GreenHopper

Dirk_Maucher
Contributor
March 19, 2012

JIRA and GreenHopper requires to set the 'Time spent' and 'Remaining Estimate' during a 'Log Work'. The prefered agile way in Scrum is to only track the remaining estimate and do not waste time in thinking about the question how much time should I log for ISSUE-4711. I was not able to find a way to shift this and only track the remaining estimate.

Is there any way to do this?

I also know that I will lose informations if we do not track the 'Time Spent' but this is okay for us.

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
boardtc
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
October 21, 2012

The remaining estimate can be tracked via the hours burndown chart. For this to be accurate the remaining time should be cleared to zero when an issues is closed. Alternatively a post function can be added which does this automatically and this will be reflected in the burndown.

0 votes
Radu Dumitriu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 12, 2012

Ok, 2 cents about: "only track the remaining estimate". This is totally bogus (I know, I know, scrum teams do not want to actually disclose how much wasted time there's in a project, and I understand why). This is where agile looses in front of traditional methods (well, I also have to say that actually I never saw a self-organizing team - some people are just born leaders and that's immediately seen in any team). Please split the theoretical scrum from the practical one.

That being said "how much time should I log" is a question about team discipline. It is good & important info. Keep track of it. It's just sane ;)