JQL doesn't display percent complete

In JIRA the epics display a percent complete if you hover over the status bar.  When I run a JQL on my epics though and display the 'percent done" field it is always blank on the results.  How can I pull the percent complete that shows on the status bar of the epics?  Obviously the data is available based on the story points since it displays on the epics but other than on that page I cannot seem to pull this information on a JQL.

1 answer

Hi Linda,

Did you manage to find out how to work with that?

I cannot even find a 'percent done' field (custom or system field) in our Jira so I'm curious how you got to this conclusion.

I can see the "0% of estimated work done (0 of 0 Story Points)" for Epics that use story points when hovering over the Epic progress bar (only with Scrum boards) but I don't think there's a field available from the Jira GUI that you can search with JQL to get the percent done.

There are 'Remaining Estimate' and 'Story Points' fields available to display values from a filter but that does not seem to match what you are looking for.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

420 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you