Hi!

I have a dashboard dedicated to agile metrics, but I can't seem to find where to change the data that Jira is using to generate the sprint health chart.
I want to generate the chart based on the Story Points, but right now it's showing data based on the Original Time Estimate.

image.png

 

Does anyone know where I can change to Story Points to generate this gadget?

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 17, 2023

Hello @Isabelle Okuma 

Welcome to the Atlassian community!

The Sprint Health gadget will automatically use the value you specified for the Estimation Statistic for your Scrum Board. If you want to change the gadget, you'll have to change the Estimation Statistic for your board. For a Company Managed project board you would find that under Board Settings > Estimation. For a Team Managed project board you would find that under Project Settings > Features > Estimation.

Isabelle Okuma April 18, 2023

Hi, @Trudy Claspill !
Thank you very much for the help! It worked :D 