Issues missing workflow after a new workflow was applied to the project

TheMoody August 29, 2012

I had several projects that was using the default workflow and recently modified them to have our new implemented workflow.

An example issue I have is in Open status but has no workflow now. The default workflow allowed it to go to "In Progress", "Resolved" and "Closed". The new workflow only allows Open to go to "In Progress". Why is the In Progress not showing and how can I fix this?

This has occurred on hundreds of issues as we have updated many projects.

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 29, 2012

Have a look at the new workflow - have you got the right transitions in place, and do the "conditions" on the transition allow your user to execute it?

TheMoody August 29, 2012

That was it, some of the transitions had conditions on them that would only let the assignee take action. I've removed conditions and all have the workflow visible now. Thanks!