Issue with losing view of in progress issues when closing sprint

Kristine Gemici
Contributor
March 5, 2024

When I complete a sprint while there are still "in progress" tasks, I lose the view of that sprint and the associated tasks within that sprint in the backlog view. I can eventually find the issues by going into the issues area but I was hoping that I could somehow see the tasks that were left in each sprint bucket and then just move them into the next sprint. Is there a way to do this? 

 

 

1 answer

1 accepted

3 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 5, 2024

Hello @Kristine Gemici 

From the Reports section of the agile board you can review the sprint Burndown Report to see all the issues that were in the sprint, which includes a section for incomplete issues.

Screenshot 2024-03-05 at 4.12.56 PM.png

Also, when you click the Complete Sprint button you should be getting a pop-up that tells you how many issues where completed and how many issues are incomplete, including an option to move the incomplete issues to the backlog, a new sprint, or an existing sprint.

Screenshot 2024-03-05 at 4.15.13 PM.png

John C
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 5, 2024

Hi @Kristine Gemici - I agree with what @Trudy Claspill said.

The reason you are given a choice as to what to do with the incomplete issues is because in Scrum - in theory - each Sprint should/could have a new and different Sprint goal, which needs a possibly different set of issues to achieve.  Jira then gives you a choice of whether to return the incomplete issues to the Backlog for consideration in a later Sprint, or to just designate them to another Sprint (such as the next Sprint) when Completing the current Sprint.

Like Kristine Gemici likes this
Kristine Gemici
Contributor
March 6, 2024

Thanks so very much Trudy & John!! That is what I needed to know! Greatly appreciated!

Like John C likes this