Hi everyone,
i created a new workflow and added this to an existing project through the "Workflow Scheme ".
the problem i have is that when moving sub-tasks to 'done' the resolution remains "unresolved" , the tasks are basically not closed.
Do you have any idea what i missed in the configuration?
Thank you,
Tali
If you want a status change to set the resolution, you either need to add a screen, with resolution as a required option, or else set the resolution explicitly in a post function. From your description, you probably want the latter.
Click on the line connecting "All" to "Done", then you should get options for that transition (Conditions, Validators, Post-Functions, and probably Triggers). Select Post-Functions and add a function; it should be a straightforward wizard at that point.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks a lot! it helped..
but now if i moved the task from done and the resoultion is resolved, if i move it back to any other status it remains resolved and doesn't get updated.
any idea?
Thanks again
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to add a post-function to clear the resolution; typically there is just one transition out, to "re-opened", or something along those lines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.