Is there any report in Jira for iteration planning to see how many hours each Resource has and how many hours hours are left? I need before the sprint start.
for example- if the below data is there and all the resources has 60 hrs total capacity-
name sub-task. Hours consumed
neelam. coding. 5
jen. Testing. 4
mahika. Test plan. 4
mahika. Defect. 6
neelam. Testing. 4
jen. Review. 4
report I want-
name. Total capacity. Hours consumed
mahika. 60. 10
neelam. 60. 9
jen. 60. 8
This app looks like that you need https://marketplace.atlassian.com/apps/1218151/capacity-tracker?hosting=cloud&tab=overview&_ga=2.135707761.1716697838.1579461263-954212144.1570005741 . It has many customers and good reviews.
Hope it will help you
Hello @neelam annad
Unfortunately, Jira out of the box does not have the concept of a resource's capacity. For this functionality, Atlassian provides Portfolio for Jira in which you can create teams, manage their capacities and plan your future roadmaps.
You can try the add-on for free for 30 days before committing to it.
If this is not preferred, there are other add-ons that the community has suggested in a previous post.
Hope this helps,
Danny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am using Portfolio plug-in and Couldn’t able to understand as how plugin calculates capacity. When we do the calculation in excel it works fine but the same in team plan says over burn...no matter if we try with story points or hours
can you help as how Jira portfolio plug-in does the over burn calculation in terms of story points and hours..
what should we do to match excel calculation with what team plan says...