Is there a way to set hours per day on a project basis?

As far as I know, the hours per day setting is a global setting. There is an issue that has been raised for this but it has been sitting there for almost 9 years!

Really seems like basic functionality that is simply being ignored...

Is there any workaround for this?

We have teams that are using different working hours and need some type of solution, which is NOT to go out and buy another plug-in, i.e, Tempo Time Planner.

1 answer

0 vote

I'm afraid not, plain JIRA still has a single global hours-per-day setting.

The only workarounds are the ones you fear - install plugins that can handle it.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

158 views 1 17
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you