Is there a way to set hours per day on a project basis?

As far as I know, the hours per day setting is a global setting. There is an issue that has been raised for this but it has been sitting there for almost 9 years!

Really seems like basic functionality that is simply being ignored...

Is there any workaround for this?

We have teams that are using different working hours and need some type of solution, which is NOT to go out and buy another plug-in, i.e, Tempo Time Planner.

2 answers

This widget could not be displayed.

I'm afraid not, plain JIRA still has a single global hours-per-day setting.

The only workarounds are the ones you fear - install plugins that can handle it.

This widget could not be displayed.

I have had this request too, has there been any update or workaround tools that could help with this? 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

280 views 1 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you