Is there a way to display due date in subtask section?

Hi guys

I do have a requirement to display a due date to next to each sub task created under parent ticket. please look at the attached screen shot for better idea.

Is this possible or any workaround?

is there a reporting way which will only take subtasks to report displaying summary, and other necessary information1.png

2 answers

2 accepted

1 vote
Accepted answer

In General Admin, go to Advanced settings, and have a look for the set of fields listed for jira.table.cols.subtasks - you should be able to add duedate to it.

Thank you for sharing your knowledge. 

0 votes
Accepted answer
Mikael Sandberg Community Champion Nov 17, 2017

As a Jira admin you can configure which fields are being displayed by editing the value of jira.table.cols.subtasks, see https://confluence.atlassian.com/adminjiraserver/configuring-sub-tasks-938847874.html

Thank you for sharing your knowledge. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,089 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you