Importing multiple Work Log entries, from a CSV file, for a single issue

Hi,

We are currently using JIRA 5.1.3.

From my CSV file I am trying to import into a project, multiple work log entries that are associated to a single issue. The only option available, when doing the import is 'Work Log (in seconds)'.

Is there a process for capturing this information?

kind regards

Amrik

1 answer

1 accepted

Accepted Answer
1 vote

Hi Amrik,

The Work Log field captures the time spent on a task. Are you trying to import time spent entries or text based updates?

https://confluence.atlassian.com/display/JIRA/Importing+Data+from+CSV - gives information on the types of fields and the methods of importing information into these.

Cheers

Dan

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

29 views 0 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you