Importing multiple Work Log entries, from a CSV file, for a single issue

Hi,

We are currently using JIRA 5.1.3.

From my CSV file I am trying to import into a project, multiple work log entries that are associated to a single issue. The only option available, when doing the import is 'Work Log (in seconds)'.

Is there a process for capturing this information?

kind regards

Amrik

1 answer

1 accepted

1 vote
Accepted answer

Hi Amrik,

The Work Log field captures the time spent on a task. Are you trying to import time spent entries or text based updates?

https://confluence.atlassian.com/display/JIRA/Importing+Data+from+CSV - gives information on the types of fields and the methods of importing information into these.

Cheers

Dan

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

1,239 views 5 10
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you