I closed a sprint and later discovered an issue that was never accepted for the closed sprint. I then accpected the story in the current sprint and did a bulk update to change the sprint but the issue is still showing up under the "Issues Not Completed" section and I am not receiving credit for the story points in that sprint. How do I get credit for the story points in that sprint?
I'm afraid you don't - as far as JIRA is concerned, it wasn't dealt with in that sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.