I need to update the total story points in a closed sprint

John DeJulio
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 5, 2017

I closed a sprint and later discovered an issue that was never accepted for the closed sprint.   I then accpected the story in the current sprint and did a bulk update to change the sprint but the issue is still showing up under the "Issues Not Completed" section and I am not receiving credit for the story points in that sprint.   How do I get credit for the story points in that sprint? 

2 answers

0 votes
Usman Kotwal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 21, 2018

Hi @John DeJulio,

did you find a solution to this?

Where did the story points go?

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 5, 2017

I'm afraid you don't - as far as JIRA is concerned, it wasn't dealt with in that sprint.

Suggest an answer