Hello,
I tried creating an automation to sum the sub-task original estimate and update to the parent task/story.
I am getting the below error. Anyone here has faced the same?
Is this smart value this...
{{#=}}{{issue.subtasks.original estimate.sum}} / 60{{/}}
...?
---
Also, I find it best to set both Original and Remaining Estimate when doing this.
Ste
Hey Stephen, it worked. My smart value was wrong. I changed it to {{#=}}{{issue.subtasks.original estimate.sum}} / 60{{/}}
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can just set both fields in the Automation Rule's Edit Issue action - Remaining Estimate is a separate field.