How to remove the Done check mark next to a ticket that was reopened? Edited

We have an issue with JIRA where tickets that are resolved but then reopened, are still marked as “done”. Do you know how to fix this?

 

1 answer

2 votes
Jack Community Leader Sep 16, 2019

you need to edit the workflow and use a Post Function to clear the Resolution for the transition out of Done to reopen.

Could you say this again in English? Maybe with some screenshots?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted in Jira

Demo Den Ep. 7: New Jira Cloud Reports

Learn how to use two new reports for next-gen projects in Jira Cloud:  Cumulative flow diagram and Sprint burndown chart. Ivan Teong, Product Manager, Jira Software, demos the Cumulative ...

246 views 1 2
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you