Hi ,

I have epics under the scrum board which have tasks with just due dates for tracking.(I do not have any estimates/story points).

These are just tasks to be tracked against due dates.

Is there any way possible to produce reports for epics in this case?

2 answers

0 votes
Sami Linnanvuo {Screenful}
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
January 21, 2020

Hi @Shubha The Screenful Metrics for Jira has an Epic report that can provide you this information. Here's an example: 

Screenshot 2020-01-21 at 10.03.23.png

The columns on the right side are configurable. You can choose to show "Overdue > 5 days", "Overdue > 10 days", "Due < 5 days" etc. Clicking the ovals reveals the individual issues. You can learn more about this chart at the Tour page

0 votes
Deepanshu Natani
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 5, 2020

The report should contain epic, its related tasks and "Due Date" field for tasks?

Shubha
Contributor
January 6, 2020

Yes ,with an overall picture in terms of percentage completion.