How to predict release date in Jira?

Hello,

I have a few questions

 

Let`s assume I have 2 user stories with the following estimates

US1 - 16 ideal hours

US2 - 8 ideal hours

and I know that a team could cover 8 ideal hours of work per day.

 

Is there an add-on or any other way to predict release date in form of burndown chart in Cloud Jira for the following cases

1. If everything is fine. In this particular case, It would be in 3 days. 

2. If estimates for US2 changed from 8h to 16h during the development, I would like to see the original date(3 days) and the new one(4 days)

 

Regards

0 answers

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

433 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you