I am trying to get historical sprint information for a few next gen projects. I want to get total completed story points for each sprint.
I want to see sprints from the beginning of the year. However, I can only see the most recent 7 sprints. There were 4 sprints before this.
Is there a way to see the velocity report for all sprints for a board? I tried to manually pull the data with advanced issue search, but I am having trouble getting accurate data (story points aren't lining up with what I expect).
Hi @Hananiah
There are some newer and some very old suggestions to change the number of sprints shown on the velocity chart, including this one from 2012: https://jira.atlassian.com/browse/JSWCLOUD-6034
No telling if that will be implemented. And, one common agile idea is looking back too far in the history isn't relevant to forecast and consider the impacts of team improvements. Regardless...
Two work-around options are to purchase an addon from the marketplace with different reporting features, or to export the items to a spreadsheet, parse the list of sprint values, and re-create the chart for older sprints.
Best regards,
Bill
Hi @Bill Sheboy,
Thanks for your response. It's good to know that this is a request. I just added my vote.
I did effectively try the spreadsheet option by using advanced issue filters. I don't 100% trust the numbers but they may serve for my purpose.
I will also look into plugins - I hadn't thought of that. Thanks for the suggestion.
H
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Hananiah Did you ever find a good plugin that worked for you? We are in the same position where we want to view previous sprints.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Kevin CrayYes I did get a plugin, I forget which exact one but it probably doesn't matter which exact one I picked since we just used it temporarily.
I just signed up for a free trial, wrote down the previous sprint numbers for that project, then deactivated the plugin so I didn't need to pay ongoing. Now I make sure manually wrote down the sprint numbers from the default velocity point report so that we can get to those in the future.
I hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi.
Does anyone know how to extract the commitment and completed data points used for the velocity reports earlier than the last 7 sprints? Or at least tailor this report to pull data from further back.
Just seems very rudimentary reporting capability for such a normally adaptive tool in general?