How to complete a sprint with parallel sprints?

Rafaela Sobral
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 26, 2022

Hi

We have parallel sprints enabled in our project, but we don't understand how can we complete past sprints

2 answers

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 26, 2022

Hello @Rafaela Sobral 

Welcome to the community.

If you have multiple sprints that are active (started) and not yet ended, on your board you need to select just one sprint to display from the All Sprints list...

Screen Shot 2022-10-26 at 4.52.00 PM.png

 

...and then the Complete Sprint button should be enabled.

Screen Shot 2022-10-26 at 4.52.15 PM.png

0 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 26, 2022

Hi @Rafaela Sobral , welcome to the community.

an active sprint should display on the Active sprint board. From that board you should be able to complete the sprint. Is this not the case? Could you share a screenshot of what you are seeing?

Suggest an answer