Hello,
I've searched in automation but I can't manage...
How can we automatically assign to a ticket the start and end dates of the sprint to which it belongs, in the fields "Start date" and "Due Date" ?
{{sprint.startDate}} => Start date
{{sprint.endDate}} => Due date
Thank you for your help !
Best regards
Aline
Thanks you for your answer, Marc, but it doesn't work :
"Error when editing tickets
TSS-1 (duedate must be in “yyyy-MM-dd” format (duedate), Start date must be in “yyyy-MM-dd” format (customfield_10015))"
... a problem with the date format
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The rule below works, but only when a sprint has been started.
(hope you're fluent in french ;o) )
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Adding to the suggestions from Marc...
Please note an issue's Sprint field is a list of values. Thus when an issue "carries over" as incomplete from a prior sprint, the field now contains at least 2 sprints.
Thus it will help to know when you want to set the Start Date and Due Date values, and what they should contain:
For example, if the rule trigger was not Sprint Started, you could set the date values for the issues in the sprint using these expressions:
{{#issue.sprint}}{{#if(equals(state, "active"))}}{{startDate}}{{/}}{{/}}
{{#issue.sprint}}{{#if(equals(state, "active"))}}{{EndDate}}{{/}}{{/}}
Or, if you assume the needed sprint is always the one with the latest dates, these would work:
{{issue.sprint.startDate.max}}
{{issue.sprint.endDate.max}}
Kind regards,
Bill