How to add multiple Projects to Advanced Roadmap after the Roadmap is created?

Kevin Lu
Contributor
July 24, 2024

Dear Jira Experts,

The organization I am working for is using Jira Data Center (it has Advanced Roadmap feature) and currently we have created a Roadmap under Plan. However, it currently tracks 1 project.

For example, in the below screenshot, we can import multiple projects under Issue Sources

page 01.png

In the below screenshot, it is a Roadmap with only 1 project. Now how do I import more projects to the Roadmap called "Test Project 1 Advanced Roadmap" after this roadmap is created? Where is the place that I can import multiple projects to the roadmap?

page 02.png 

Thank you in advance!

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 24, 2024

Hello @Kevin Lu 

Click on the gear icon next to the Roadmap name and select Configure.

That will open a page where you can get to the configuration options for the Plan including the configuration of the data sources.

Screenshot 2024-07-24 at 4.38.36 PM.png