I use JIRA 4.4.1 and Green Hopper 5.7.4.
I added two more issue types in JIRA. But these are not available in Agile planning board.
How to add this to Agile ?
Guys,
This is fixed.
The issue was, I disabled versionning in some projects.
Thanks, Vishnu
Are your new issue types available in the regular jira screens for your project ?
GreenHopper just picks up the same list of issues types which are available to the project you have selected. So if you can't see it in Green Hopper I would suggest that the either:
Do any of these help?
I assume that the two issue types aren't associated to the GreenHopper Issue Types Scheme. Just go to "Manage Issue Types", select the second tab "Issue Types Schemes" and associate the two issue types to the GreenHopper Scheme.
Hope that helps,
Sebastian
All issue types are available in the project home page. I can create all issue types.
Ok, so when you go to the Planning Board and you have selected your project.....
There is the normal "Create Issue" at the right end of the menu bar.... is the current project selected? Do you see the full list of isssue types?
Then, look at the "New Card" button in (next to views / Tools on RHS). Click it & you will get a pop up.
In the drop down on the top LHS should be the list of issue types & should be the same as the "create issue" list of issue types.
If it isn't either there is something not in the problem description or your Jira/GH is very broken, or your Browser is caching information, page reffresh maybe?
Matthew,
Thanks for the help.
I see all issue types at the 'Create Issue' and at the 'new Card' operations.
I created new card. Even this issue is not in the planning board.
Thanks, Vishnu.
Vishnu, change your view to "project overview" and check whether they are visible. While adding the new card, did you select any fixversion for the issue?
Renjith,
I tried all options like 'Project Overview', assginee etc.
I haven't selected any Fix versions.
One other thing no-one has asked yet, but is worth ruling out. Your new issue types - are they sub-tasks? They can only be created underneath top-level issues, so they don't appear on the create menu in GH (or Jira for that matter)
Nic,
These are not sub tasks.