How to add field of Epic link when I create story issue?
Based on my project creation as team-managed type, there is no Epic link field when I try to create the story issue.
However, I have seen from other projects as company-managed type that there is this field available, so I'm not sure if it's because the default configuration between the project types is different?
Are there any ways for me to add this field available into my project?
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Adding to what @Hamza Chundrigar
If you have used the Create button from the menu bar to start the creation of the issue in a Team Managed project you can't specify its parent Epic during that process.
If you want to create an issue and have it be created as a child of an Epic you have these options:
1. While viewing the Epic click on the "Add a child issue" button.
2. Click on the "+" button int he Child Issues section of the Epic.
If you have already created the issue and need to add it to an Epic your options are:
1. Click on the "Add epic" link in the bread crumbs when viewing the issue.
2. If you have a Backlog screen enabled and the Epics Panel enabled, dragged and drop the story onto the Epic.
3. In the Backlog screen hover over an issue and the "+Epic" button will display.
4. On a board, click on the "..." button for a card and choose "Add parent"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Great addition @Trudy Claspill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.