How is the progress percentage calculated for issues?

Brad Newman October 4, 2011

How is the progress percentage calculated for issues?

3 answers

1 accepted

0 votes
Answer accepted
Brad Newman October 20, 2011

Time Spent / (Time Spent + Time Remaining)

0 votes
Markus Lepper
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 6, 2011

It's "time spent/time estimated".

Brad Newman October 6, 2011

But there's no actual field for "time estimated" right? By time estimated do you mean "Time Spent + Time Remaining"?

0 votes
Brad Newman October 4, 2011

Is it: Time Spent / (Time Spent + Time Remaining)?

1.