How is the Predicted Completion Date and Velocity exactly calculated

Hi all,

as you can see from the title, I am trying to figure out how the above figures are exactly calculated in the Version Report.

I could not find exact definitions, and it also does not make quite sense to me. In one definition it says that velocity is calculated as the average from prior sprints. But somewhere else it says, it takes the daily velocity. So how is that possible, then?

Also, what is the excat formula for the predicted completion date?

An answer to that would be greatly appreciated, as I am trying to find appropriate reports for our oranization.

Many thanks in advance and best regards,

Justyna

1 answer

This widget could not be displayed.

I am also wondering why it says that I should provide an answer to my own question? (Possibly weird question, but sorry, am a newbie...)

You might want to delete your "answer", because otherwise your question will not show up in overviews of unanswered questions, so that you might not get any.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

139 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you