In order to show your Story Estimate on your board issues, perform the steps below:
- Navigate to your project > Project Settings > Screens
- Add the field Story Points Estimate to your view/edit Screens
- Navigate to your board > Board Settings > Card Layout > Add the field Story Points Estimate to your backlog cards
Hi Petterson,
Thanks for the reply! I don't have a 'screens' setting under the project? I'm administrator for everything.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Alex,
It seems you are using an Agility project. The Agility template is a new and simple template used for simple use-cases, where customization is not allowed.
To do the kind of customization you are looking for, please create a new project with the Scrum or Kanban template.