How do I show story point values on the story card when the story has sub tasks?

Shane Wang-Pote June 21, 2018

I am trialing Jira and when I have a story that has sub tasks the story point estimation is not show on the story card.  If I have a story without sub tasks then the story point is shown.  This is on the sprint board.

1 answer

0 votes
Mesut Yilmazyildirim
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 21, 2018

You can set estimations for sub-tasks and stories separately. Please be sure that you entered estimation for all issues.

It will be also better to share a screenshot to understand the details.

Shane Wang-Pote June 21, 2018

Screen Shot 2018-06-22 at 07.51.34.png

From the screenshot you can see that PW-16 has a story point estimate displayed on the board, it has no sub tasks.  But PW-14 doesn't show and it has sub tasks.  I do not want sub tasks to have story points only the story must have points.

Mesut Yilmazyildirim
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 21, 2018

That's clear now.

The swimlanes are configured on Stories. If you set swimlanes to "no swimlanes" you can see all estimations

Shane Wang-Pote June 21, 2018

Thanks for your answer Mesut.  I think I prefer the swimlanes though.  Looks like I will have to deal with it.  Have a great day.