How do I change the sprint start date in Portfolio?

This is for a new install of Portfolio. The documentation says that sprint start dates are based on the start date for releases. I have 3/16/15 set for all of my releases but my sprints are starting on 3/23 which is one week off for my 2 week schedule.

Everything in the backlog is set to the same date (3/16). 

 

Removing Earliest Start dates from all of the backlog items and letting it calculate still has sprints starting on 3/23.

3 answers

1 accepted

1 vote

Hi Justin, sprints are indeed expected with the start date of the first release configured in the releases tab. If there are multiple release streams, the earlierst release across all streams is taken for the start of the first sprint. It should not be necessary to set any start dates on the items themselves. 

That said, there might be another root cause why it behaves differently.

Have you done a plan update as part of trying the product? You could see that if you look at the first label in the timeline: Does it say "23/3 - Start" or "23/3 - Update" ? An update is normally used to keep the plan updated regularly, and "plan forward" from a given point in time, thus the start date is moved forward as well to what you set in the update from date dialog. If this is the case, you can "reset" the plan update date by choosing "Plan > Update from date", and select a date prior to March 16 - always the later date of the release and plan udpate is taken. 

If you can't make sense of it still, feel free to send along/attach an anonymous plan export (Plan > Export > Render data anonymous) so we can take a quick look. 

Cheers, Martin

Hi - are you please able to advise how to do this in Portfolio 2.0

thanks

Hi, where can I find "Plan > Update from date"? Thank you

@Martin: Where do I find Plan->update from date?

Martin I'm New Here Feb 16, 2018

@Christian Waidner Sorry, wrong Martin.

Do you know where I can find similar in Portfolio 2.0?

Did you figure it out?

Martin, thank you! I looked at that forever and remember reading about the Update From Date so thanks for the reminder. I set it for 3/2 and it all fell into place with the correct dates for our sprints. Thanks a bunch.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,316 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot