How do I add pre-existing field to sub-tasks?

I need to add the Original Estimate field  (or something similar) to sub-tasks as they are estimated separately from the Story. We are a multi-discipline team so to complete a Story (essentially a feature) I have to break out sub-tasks per discipline.

The scheme I am using is Epic -> Story > Sub-task 

We are using JIRA Cloud 

Version1000.253.3

2 answers

1 accepted

0 votes
Accepted answer

Check the field configuration for the sub-tasks, and ensure that does not hide the "time tracking" field.

Then go to the project "issue type screen scheme" to identify what screen schemes are in use by the sub-tasks.  Inside those, there are a list of screens in use - make sure time tracking is added to the create and edit screen.

Worked like a charm. Many thanks!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,397 views 15 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you