How do I add pre-existing field to sub-tasks?

James McNeely August 18, 2016

I need to add the Original Estimate field  (or something similar) to sub-tasks as they are estimated separately from the Story. We are a multi-discipline team so to complete a Story (essentially a feature) I have to break out sub-tasks per discipline.

The scheme I am using is Epic -> Story > Sub-task 

We are using JIRA Cloud 

Version1000.253.3

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 18, 2016

Check the field configuration for the sub-tasks, and ensure that does not hide the "time tracking" field.

Then go to the project "issue type screen scheme" to identify what screen schemes are in use by the sub-tasks.  Inside those, there are a list of screens in use - make sure time tracking is added to the create and edit screen.

0 votes
James McNeely August 18, 2016

Worked like a charm. Many thanks!