August 18, 2016

I need to add the Original Estimate field  (or something similar) to sub-tasks as they are estimated separately from the Story. We are a multi-discipline team so to complete a Story (essentially a feature) I have to break out sub-tasks per discipline.

The scheme I am using is Epic -> Story > Sub-task 

We are using JIRA Cloud 

Version1000.253.3

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 18, 2016

Check the field configuration for the sub-tasks, and ensure that does not hide the "time tracking" field.

Then go to the project "issue type screen scheme" to identify what screen schemes are in use by the sub-tasks.  Inside those, there are a list of screens in use - make sure time tracking is added to the create and edit screen.

0 votes
James McNeely
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 18, 2016

Worked like a charm. Many thanks!