How can you add time estimate to a sub-task in scrum?

We are new to jira and are using scrum project set-up with tempo time tracking. We have just started using sub-tasks. How can we add time estimates to these?

1 answer

0 votes

The default for Jira is to allow time estimates in most ways, but not put the field you need on the create or edit screens.  Go to the project configuration, and find the "screens", descend into them and add "original estimate" to them.  You'll need to be an admin to do it.

But.  Don't try to use this for velocity or Scrum.  Jira Software won't handle it usefully.  Estimation really needs to be done at a story level, not sub-task.  (There's an essay answer on why this is the case with Jira, with a lot of whinging from me at both Atlassian and their Customers, which I won't bore you with)

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,760 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot