I would like to add a column for time spent on a story, that adds up the values from the subtasks and provides the total. I can view this with filter views, but for some reason I can't find the column and add it to roadmaps.
Hi @Rocío Bayon
The only way I know, is to show the progress in days, and then by hovering over the progress bar you can see the Time Spent.
The idea behind advanced roadmaps is planning, not reporting on what has been done.
Roadmap (Plans) is a forward looking tool, completed issues also disappear from the plan after some time (default 30 days).
There is also a limit of - if I am not mistaken - 5.000 issues at max in a plan, which may also become limitative after some time and for cross-project plans.
To report on work done towards stakeholders, it may be better to use other reporting features in Jira (or via reporting tools) better suited for the job.
Thank you Marc!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Join us to learn how your team can stay fully engaged in meetings without worrying about writing everything down. Dive into Loom's newest feature, Loom AI for meetings, which automatically takes notes and tracks action items.
Register today!Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.