How can I see story points coming from other projects in a company-managed project ?

claire_pellat
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 29, 2024

Hello,

I use different types of projects in Jira to manage in one tool my products and my teams.

So : I have several team-managed projects that represent our products.

I also have several company-managed projects that represent our teams.

In my team-managed projects (let's call them FRONT and API), we estimate stories using the field "Story point estimate". My company-managed project (let's call it TEAM1) is configured to gather all the stories from FRONT and API where the field "Team" is set on "TEAM1".

That way, my project TEAM1 allows me to see on one only board all the jobs that have to be done by my team on the products FRONT and API.

In the project TEAM1, I can't see the story point estimate on the "backlog" and the "board" views.

How can I configure my project or my board in order to see these estimations ?

Thanks very much for your help !

1 answer

2 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 29, 2024

Hi @claire_pellat 

Welcome to the community.

The field "Story point estimate" is only working with Team Managed projects, Company Managed projects use the field Story Points.

You will need to have all teams using a company managed project template.

You case doesn't fit to have teams using Team managed projects, as they are like a "silo"