I have a story with say...10 sub-tasks.  Each of those sub-tasks has a story point estimation.  Is there a way to have JIRA automatically roll those sub-tasks story points up to the parent user story to the user story gets the sum of those story points logged against it?

2 answers

0 votes

Only by coding, and most of the approaches to doing it mess up your reports.

0 votes
Steven Behnke Community Champion Jul 21, 2017

As Nic suggests, only through custom code.

A Listener could detect when subtasks are created/updated/deleted and sum the story points. The Listener could then set the value on the parent issue.

A Custom Field could be programmed to retrieve values from subtasks and sum when displaying the field.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,755 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot