I have all metrics by issue type Story,
but Story Points are inside of Sub-Tasks.
How can i change a Jira Metrics of Velocity from Story to Sub-Tasks?
Hi @Casper
You can't do that with the native in built reports in Jira reports. It is a common question but if you are using Jira Software with SCRUM board then stick to using story points at the story level. You can always use apps like eazyBI to create a custom report or do some automation to roll up estimates from subtasks to stories.