Hi,
For an issue, it's showing I logged 1d 1h 25m. However that's not correct, and I must have mis-typed an entry.
However, under Activity -> Work Log, the 4 entries shown only total about 9.5 hours, far short of 24+ hours. Where/how do I see the other parts that make up that much bigger time count?
Thanks!
@Nykris welcome to the Atlassian community
Does the issue have sub-tasks? Is the "Include subtasks" checkbox in the parent issue's settings checked? If yes for both do the hours of the issue and sub-tasks hours add up to the total hours logged?
Jira allows you to see the hours of the parent and the sub-tasks on the parent. You can up check the box then it will only show the parent.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.