Is there are way to create a filter which will report on scheduled/planned hours for a staff member?

2 answers

1 accepted

Hi David,

There is an inbuilt report available for this information. Simply navigate to the desired project, select 'Summary'. Towards the bottom of the page will be a heading 'Reports'. This contains the 'User Workload Report'. Select this and enter the desired users profile.

For further information on this report please check out the following great guide: https://confluence.atlassian.com/display/JIRA/User+Workload+Report

Cheers,

Paul

This gives the number of issues assigned. In my question I was referring to planned hours...

Hi David,

The third column of this report in JIRA OnDemand is 'Workload' and contains the total workload remaining for the selected user.

I've also attached an example from my instance to demonstrate the report:

Thanks,

Paul

I was really after a way of getting this information from a filter which I could then use to show in dashboard gadgets...

Hi David,

To create a filter that replicates this behaviour you would need to query on the assignee field. You would also need to add the 'Remaining Estimate' column via 'Tools' >> 'Configure Columns'. This query could then be saved for reuse. You are also able to export this to Excel if required. Finally, you could add the gadget, 'Assigned to Me' on the dashboard and include the field 'Remaining Estimate' in the section 'Fields to display'.

Hope this helps :)

Cheers,

Paul

I want the filter to give me "Planned Hours" not "Remaining Estimate".

Hi David,

Are you using Tempo? I cannot see this mentioned earlier in your query which is why I had suggested 'Remaining Estimate'? The 'Planned Time' field is not a standard field in JIRA OnDemand.

The Tempo plug-in is a 3rd party supported plug-in but I searched further for you and found the following documentation which shows a Tempo gadget that reports on the planned time per user: https://tempoplugin.jira.com/wiki/display/TEMPO/Tempo+6.2+Release+Notes#Tempo6.2ReleaseNotes-TimePlanning

Thanks,

Paul

Hi Paul, sorry I didn't mention that. Yes we are using tempo...

Thanks David,

You will see a link above in the original comments for the time planning gadget for Confluence dashboard which reports on planned hours versus worked time.

Cheers,

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,241 views 14 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot