Epics requires acceptance criteria

Dev April 26, 2019

Hi there,

How can I ensure that for the story type "Epic" the field "Acceptance Criteria" and due date is required?

1 answer

0 votes
Ollie Guan
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2019

Hi @Dev ,

Classic project or Next-gen project?

Dev April 26, 2019

Classic Project

Ollie Guan
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2019

Can you find this field in the field configuration and set it as required?

duedate.jpg

Dev April 26, 2019

Yes, but I only want the "Epic" story type requiring Acceptance criteria and Due Date

Ollie Guan
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 26, 2019

You need to split the IssueType and field schemes, and Epic needs a separate custom field scheme.Pls refer to the following tips:

Associating an issue type with a field configuration

捕获.JPG

Suggest an answer

Log in or Sign up to answer