Hi,
I am creating an event (E) to be occur at a future date and I want the subtasks to reflect SLAs that are back calculated from this event date (E-5 days or E-2 days).
Any help would be greatly appreciated as I am only able to create automation from a 'Create Date' standpoint.
Thanks
Hi @Shikhar Madan -- Welcome to the Atlassian Community!
I am unclear which date you are trying to use. You could use the automation date / time function to subtract the value needed: https://support.atlassian.com/cloud-automation/docs/jira-smart-values-date-and-time/#Date-minus-unit---
If that does not help, for a question like this, context is important for the community to help. Please post the following:
Kind regards,
Bill