Do not understand where the remaining points for In Progress (story points) are being rolledup from

Neil Wills May 30, 2023

screenshot.png

There is 1 un-pointed story.

There other stories that are remaining do not roll up to 124 points, and there are no estimates in the other estimate fields.  The plan is set for story points.

Capture.JPG

 

1 answer

0 votes
Mathias Richter
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 31, 2023

Hi @Neil Wills 

I would look at two things first:

  • Did the Epics also get Story Points assigned? (the roll-up is summing up all values on all hierarchy levels, not just Story-level)
  • Is there a filter applied somewhere?

The summary shows 46 estimated issues, is that the number of stories in all Epics we see in the Screenshot?

Neil Wills June 6, 2023

The solution was that the Epics had value and the stories.


The epic was automated to sum the points from its children.

With roadmap plans I can stop doing that.

 

Now to work with the teams to populate the epic story point with the estimate for the quarter to forecast the quarter, and remove it when you start decomposing stories.

 

We cannot solve having incomplete breakdowns for an epic, its agile after all.

Like Mathias Richter likes this