Difference between logging work time and adjusting the remaining time?

What is the difference between logging work time in an issue and adjusting its remaining time estimate? When use one or the other, or is it the exact same thing? This has been creating a lot of confusion in my project

1 answer

When we're logging time in our setup, we at the same time are forced to choose, what to do with the remaining estimate. The reason is, that the programmer needs to estimate, if the original estimate is still valid. If it is, then you could say, logging time and adjusting remaining estimate is the same. But if the task takes more time than original estimated, then it's two different things.

An example:

Let's say that the original estimate is 100 hours, and the programmer has worked 50 hours on the task, but his estimate is, that there's still 70 hours left. Then he needs to update the remaining estimate to 70 hours, but he will register, that he has worked 50 hours on the task.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

Meet the AUG leaders of Northern Virginia

@Rachel Wright (Jira Genie), @Billy Poggi (AUG NOVA, DC), and @Dana Jansen (Confluence Queen) are just some of the folks that lead one of the world's most active Atlassian User Group (AUG)....

125 views 4 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you