Difference between logging work time and adjusting the remaining time?

What is the difference between logging work time in an issue and adjusting its remaining time estimate? When use one or the other, or is it the exact same thing? This has been creating a lot of confusion in my project

1 answer

This widget could not be displayed.

When we're logging time in our setup, we at the same time are forced to choose, what to do with the remaining estimate. The reason is, that the programmer needs to estimate, if the original estimate is still valid. If it is, then you could say, logging time and adjusting remaining estimate is the same. But if the task takes more time than original estimated, then it's two different things.

An example:

Let's say that the original estimate is 100 hours, and the programmer has worked 50 hours on the task, but his estimate is, that there's still 70 hours left. Then he needs to update the remaining estimate to 70 hours, but he will register, that he has worked 50 hours on the task.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

97 views 1 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you