Defining weekly hours globally instead of per project

Is it possible to define a persons weekly availability across all projects?  From what I can tell, it only seems possible on a per team basis. 

In my scenerio, I have a portfolio plan with two projects.  each project has a unique epic assigned to a seporate team.  However, there is an person who is on both teams.  By default, the plan allocates the total default weekly hours to both projects, effectively double counting the time.

I can define a weekly hours value within each team the person is assigned, however this doesn't seem right.  My expectation is that the individuals weekly hours would be spread across all projects when not otherwise define explicitly.

Is what I'm after possible?  Have I set things up incorrectly?

0 answers

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

23,748 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you