Dúvida sobre como estruturar um projetos com vários entregavéis

Clodoaldo Costa
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 9, 2023

Prezados, tenho um grande Projeto onde dentro do mesmo tem vários "sub-projetos" e dentro destes existem várias atividades.

Como devo fazer para que a estrutura fique mais ou menos assim:

PROJETO -----> SUB-PROJETO----->ATIVIDADES

Exemplo:

Projeto RH ------> Consignação em folha-----> Atividades 1, 2, 4, 3, 4 ,5 etc

E como demonstrar os status destas atividades e não do projeto e dos sub-projetos? Porque quando faço isso no meu "quadro" aparecem os status, porem somente com os Projetos e não com os itens.

Obrigada

 

1 answer

0 votes
Brant Schroeder
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 23, 2024

@Clodoaldo Costa welcome to the Atlassian community

There are a couple of different ways to do this. 

Option 1

  • Projects are defined as a component and are applied to every issue.
  • Story is Sub-Project 
  • Sub-task of Story are Activities

Option 2

  • Story are Projects
  • Tasks are Sub-Project and linked to the project (Issue Link) 
  • Sub-task of Story are Activities

There are other options as well but is really depends on what you are trying to do, how you will report and what requirements are around each project, sub-project and activity.

Brant Schroeder
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 18, 2024

@Clodoaldo Costa If this answered your question can you please accept the answer to help others?

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events