Our company got several development working on few projects at same time. Developers are not strictly assgned to project, cause we are trying to use their working time as best as possible. So developers may be assigned for task from different projects.
Each project has its own structure in Jira and we got big problem with that - even if I create all dependencies between tasks, structure ignores dependencies on tasks, that are not in structure.
We have tried to create non-project structure for department, so lead could plan tasks for its developers, but it isnt work as expected - project-structures ignore time lag that developer works on task from another project.
Looks like structure isnt made for it, but what solution can I offer for departments to plan their tasks and build structures according to developers availability?
@Contemplation
Hello, if your goal is to be able to re-use automatically calculated Start & Finish dates from Gantt charts, you can achieve it with Effectors. We have a YouTube video demonstrating how a local attribute can be turned into a regular Jira field value.
But please note - Effectors don't run automatically every time when a change is made. But you can use a script to run them on a schedule and update the Jira fields with relevant data once or twice a day.
I hope this helps. If you need further assistance or have other questions about Structure, please reach out to us directly at our support portal and we'll get back to you shortly.
Best regards,
Stepan
Tempo (the Structure app vendor)
Would it be better to just create a kanban board that contains all tasks that are assigned to the specific developers? Then you could configure the swimlanes by assignee to easily see what tasks have been assigned to each developer and where along the workflow the open tasks are.
If this solution wouldn't work, could you provide more detail about what specifically you are trying to accomplish and what problem you are trying to solve?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
We got at least 5 structures with 1000+ strings for more than 1 year total duration from today, about 50+ developers and 6 depts.
Kanban board will be too massive, I guess, but i could be wrong
Problem is complex:
1. our company has projects that are using shared resourses (developers)
2. all projects planning is in Jira structures
3. if we dont link small tasks to epics - we cant predict time for release and requered human resourses
4. if each project manager use shared resourses of develorers without confirmation - we cant guarantee that compaty provide that resource, here could be collision in copmetition for exact developer, for e.g.
so, as I see, if there is an instrument, where we colud make task-chaines for each developer, and project-structures will receive all dates and updates from it in real-time, it will solve the problem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if there was an option to make Gantt Start Date and Gantt Finish Date end-to-end attributes in all structures that we use it would be perfect solution
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using Structure Gantt? We no longer use it at my current company, since Plans give us that functionality, but I used it at a previous company and I seem to recall that you could set up the dates in any of the start > start, end > start, etc. configurations.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
will look trough Plans functionality, thank you
unfortunately dates that are in "auto" mode on structures are not attribute of task, it is stored in structure, and "manual" mode ruins all benefits of using gantt